Improvements Set for Union County Intersection 

Staff Report//June 25, 2026//

Improvements Set for Union County Intersection 

Staff Report//June 25, 2026//

Listen to this article

MONROE– Changes are on the way to a busy Monroe intersection, thanks to a $1.3 million N.C. Department of Transportation contract recently earned by Sealand Contractors Corporation of Midland. 

 The project includes these changes at the U.S. 74/U.S 601 intersection: 

  

  • U.S. 601 North will be modified to include three left turn lanes onto U.S. 74 West; 
  • U.S. 74 East will be modified to feature two thru lanes and two southbound right turn lanes onto U.S. 601; 
  • The traffic signal at the intersection will be adjusted to include movements for Campus Park Drive, making this road another leg of the intersection. 

  

The intersection’s pavement will also be milled and resurfaced with new pavement markings and markers. 

The date of availability, or earliest time the contractor can begin working, is Monday, June 15. Any lane closures needed to complete the work will be limited to overnight hours between 9 p.m. and 6 a.m. 

The contract calls for roadwork to be complete by the end of August. 

 

Latest News

See All Latest News

Features

See All Features

Polls

Will the Trump Organization ever go through with a purchase of The Point Lake and Golf Club in Mooresville?

View Results

Loading ... Loading ...